Rooftop solar no longer needs a building permit in Moldova
Law No. 153 of 30.07.2026 simplified the installation of solar power plants and energy storage. It was published in the Official Gazette on 6 August 2026.

The law amended Article 150 of the Urban Planning and Construction Code. Solar panels and heat pumps can now be installed without an urban planning certificate and without a building permit.
This covers the roof, facade or your own land next to a private house (including duplexes and terraced houses), the roof and facade of buildings of any type, and, in apartment blocks, roof or facade systems that power common areas.
Energy storage can also be installed without a building permit: on the grounds of solar parks and energy facilities, and on commercial, agricultural and industrial sites.
A project is still required. Its electrical section is based on a connection opinion agreed with the system operator, that is, your grid operator. Pitched roofs and facades of buildings other than private houses need a structural assessment, and storage also needs a fire safety section.
In heritage protection zones the culture authority must give its opinion, and panels are not allowed on standalone monuments. If you are unsure whether your site qualifies for the simplified procedure, the law lets you ask the permit authority in writing: it must reply within 10 days.